The City is undertaking a project to reconstruct North 4th Avenue from East 5th to East 7th Street, including the intersections of those streets. The project also includes new storm sewer, a new water main, a new sanitary sewer, and reconstructed sidewalks. Upsized water main will be extended to East 10th Street. The general contractor for the project is Cornerstone Excavating of Washington.
As of June 16, repair of the sewer collapse at the railroad tracks was added by change order to the project. This work was completed August 29. Full plans for this change order are available below.
- 2020 11 23 N. 4th Ave. Construction Update
- 2020 11 06 N. 4th Ave. Construction Update
- 2020 10 30 N. 4th Ave. Construction Update
- 2020 10 23 N. 4th Ave. Construction Update
- 2020 10 15 N. 4th Ave. Construction Update
- LTR - 2020 10 01 - Construction Update - Property Owners
- 2020 09 23 N. 4th Ave. Construction Update
- 2020 09 10 N. 4th Ave. Construction Update
- 2020 08 28 N. 4th Ave. Construction Update
- 2020 08 17 N. 4th Ave. Construction Update
- LTR - 2020 08 03 - Construction Update - Property Owners
- LTR - 2020 07 24 - Construction Update - Property Owners
- 2020 07 20 N. 4th Ave. Construction Update
- 2020 07 13 N. 4th Ave. Construction Update
- 2020 07 02 N. 4th Ave. Construction Update
- 2020 06 26 N. 4th Ave. Construction Update
- Letter to N. 4th Property Owners- 6-11-2020
- Change Order No. 1- Sewer Collapse Repair Plans- 6-12-2020 (27MB)
- Letter to N. 4th Property Owners- 4-9-2020
- N. 4th Ave. Improvements - Single Plan Sheet
- 2019 11 01 - N. 4th Avenue Improvements Schedule
- Letter to North 4th Property Owners- 2-14-2020
- N. 4th Ave. Improvements - Full Set of Plans (69MB)